Task 10: Aligning antennas Chapter 6 Configuration and alignment
phn-1115_006v000
6-44
Sep 2010
Task 10: Aligning antennas
Before performing this task, check that hardware installation is complete (apart from
the network connections) at both the Master and Slave sites.
This task consists of the following procedures:
• Starting up the units on page 6-44
• Checki
ng that the units are armed on page 6-45
• Aligning antennas on pa
ge 6-45
• Aligning separate antennas
for spatial diversity on page 6-47
• Monitoring received signal level on
page 6-47.
• Disarming the units on
page 6-52
Starting up the units
To connect one of the units to a management PC and start up both units, proceed as
follows:
Procedure 6-15 Starting the units after site hardware installation
1
Select the unit from which this process is to be controlled; either
Master or Slave. This is the ‘local’ unit.
2
Check that the management PC is connected to the local unit,
powered up and logged on.
3
Start the local unit.
4
Start the remote unit.
5
Log into the local unit as described in Logging into the web
interface
on page 6-4.
Comments to this Manuals