PTP 300 and PTP 500 Series User Guide Installing a PTP-SYNC unit
phn-1115_006v000
Sep 2010
5-33
6
Use a grounding cable to connect the ground stud of the PTP-SYNC to
the master ground bar of the building.
Powering up the PTP-SYNC installation
To power up the installation, proceed as follows:
Procedure 5-10 Powering up PTP-SYNC
1
Ensure that all cables are connected to the correct interfaces of the PTP-
SYNC unit and the GPS receiver (if used). Ensure that the installation is
correctly grounded.
CAUTION
Failure to do so may result in damage to the equipment.
2
Connect the power supply to the PIDU Plus.
3
Within 90 seconds, the PTP-SYNC ’STATUS’ LED should blink once every
second to show that satellite lock has been achieved.
4
If the system does not operate correctly, refer to Testing PTP-SYNC on
page
8-17.