1 PTP 300/500 Series Deployment Guide Contents Protect Your Installation...
10 Mast, Tower or Building Installation Hoist and Safety Loop Use the integral safety loop for hoisting the ODU up a mast, tower or building. When t
11 Mast, Tower or Building Installation Mast or Tower Installation Instructions The ODU is pre-fitted with a mounting bracket (designed to ease insta
12 Mast, Tower or Building Installation Step 2: Offer the ODU (with pre-fitted mounting bracket) to the bracket strap and affix using the captive M8
13 Installation Wiring More information: PTP 300 Series User Guide or PTP 500 Series User Guide Section: “Lightning Protection”
14 Cable Preparation and Installation The maximum cable length between the ODU and the user’s network equipment is 100 m (330 ft). CAUTION: Check
15 Cable Preparation and Installation Cable and Gland Installation To install the cables and glands, follow these steps: Step 1: Make a cable as spe
16 Cable Preparation and Installation Step 4: When the gland body has been fitted, tighten the gland back shell. Caution! Do not over tighten th
17 Testing and Fault Finding (Troubleshooting) Perform troubleshooting (fault finding) procedures either on a newly installed link, or on an operatio
18 Testing and Fault Finding (Troubleshooting) (*1) Power LED is Off Unplug the ODU connection from the PIDU and check the power LED illumination. I
19 Testing and Fault Finding (Troubleshooting) Table 1 - Resistance Table Referenced to the RJ45 at the PIDU Resistances should fall within + or -10
2 Protect Your Installation Attention ElectroMagnetic Discharge (Lightning) Protect Your Installation! EMD (Lightning) damage is not covered under w
20 Installation and Commissioning Aligning the PTP 300 or PTP 500 Series Bridge ODUs The PTP 300 and PTP 500 Series Bridges use audible tones durin
21 Installation and Commissioning Behaviour During Installation The following behavior should be noted: • Band scan: When first started up and fro
22 Installation and Commissioning Adjust Power Settings The transmit power levels of the installed units must be adjusted to ensure they are not too
23 User Information to be Recorded Use Table 2 and Table 3 to record the specified information. This information will be useful if there is a need t
24 User Information to be Recorded User Notes
25 Registration Warranty and Ordering Information The PTP 300/500 is an extraordinarily robust radio communications link with unsurpassed availabil
26 License Keys and Regulatory Information Unit A1, Linhay Business Park Eastern Road, Ashburton Devon, TQ13 7UP, UK Telephone Support: +1 877 51
3 Protect Your Installation Lightning Protection Zones When the ODU is installed on a mast, tower or wall, it may be in one of two possible lightni
4 Protect Your Installation Additional Grounding Requirements for Connectorized ODU Where the ODU is mounted outdoors and is mounted some distance
5 Checklist, Site Survey and Tools CAUTION: Before performing an installation of a Motorola PTP 300 or PTP 500 Series system, ensure that you have re
6 Bench Testing (Optional) It is advised that the link be configured and tested on a bench before the final installation of the units on a pole or a
7 Bench Testing (Optional) NOTE: If the power LED does not illuminate, remove the power cable and the ODU connection from the PIDU Plus. Re-connect t
8 Bench Testing (Optional) Configuration Checks Step 1: Use a web browser to connect to IP address http://169.254.1.1 for Slave and http://169.254.1
9 Bench Testing (Optional) Step 4: Access the ‘Installation Wizard’ page. Confirm the target MAC Address, Master/Slave choice, Symmetry, Max Transmi