Mast or tower installation
For mast or tower installations, the following additional requirements must be met:
The equipment must be lower than the top of the tower or its lightning air terminal.
The metal tower or mast must be correctly grounded.
A grounding kit must be installed at the first point of contact between the drop cable
and the tower, near the top.
A grounding kit must be installed at the bottom of the tower, near the vertical to
horizontal transition point, bonded to the tower or its ground bar (TGB).
If the tower is greater than 61 m (200 ft) in height, an additional grounding kit must
be installed at the tower midpoint and as necessary to reduce the distance between
ground kits to 61 m (200 ft) or less.
In high lightning prone geographical areas, additional ground kits should be
installed at spacing between 15 to 22 m (50 to 75 ft). This is especially important on
towers taller than 45 m (150 ft).
A schematic example of a mast or tower installation is as follows: